Project Milestones Start: 01/09/2016

01/09/2016: Grant Agreement signed with the European Commission and kick off meeting of the project

January 2017: Target technical specifications of the microturbine and RTU defined



July 2017: Detailed design of microturbine and RTU carried out

March 2018: Prototype manufacture completed and the first fully assembled units ready to begin testing

April 2018: CE marking achieved according to ATEX Directive, Machinery Directive, and Electromagnetic Compatibility (EMC) Directive